RadonPlans

Manitoba radon requirements for new construction

Manitoba Building Code, M.R. 78/2023 (adopts NBC 2020), Subsection 9.13.4In force since April 1, 2011

What your permit set must show

  • Manitoba's radon rough-in provision has been in the province's legally binding building code since the 2010 NBC model code was adopted, and is carried forward in the current Manitoba Building Code, M.R. 78/2023 (which adopts NBC 2020).
  • Requires the same rough-in stub pipe provision as BC, Alberta, and Ontario, applied province-wide.
  • Applies to all new Part 9 residential buildings under the current code.

Common questions

How long has Manitoba required this?

The radon rough-in provision has been in force since April 1, 2011, when the 2010 NBC model code was first adopted, and has been carried forward through subsequent code editions including the current M.R. 78/2023.

Is this province-wide?

Yes, with no exemption found in the current Manitoba Building Code.

Get notified when we cover Manitoba